September 2016: St. Petersburg, FL. Yacht Basin
Land & Sea Surveying performed a single beam hydrographic survey of the N. Yacht Basin at St. Petersburg Municipal Pier to verify sufficient depth for incoming vessels.
September 2016: Tampa Convention Center
Land & Sea Surveying performed a single beam hydrographic survey of the berthing area at the Tampa Convention Center to determine sufficient depth for incoming vessels.
September 2016: Port Canaveral, FL.
Land & Sea Surveying performed a single beam hydrographic survey in Port Canaveral to locate a HDD cable. Land & Sea also provided divers to mark the location of the cable.
Land & Sea divers set buoys to mark the location of the HDD cable as shown just below.
Land & Sea Divers locating the cable just above.
September 2016: Squidlips in Sebastian
Land & Sea Surveying performed a single beam hydrographic survey for Squidlips in Sebastian to obtain a FDEP permit for proposed docks. Land & Sea also provided divers to investigate and mark the location of sea grasses in survey area.
Below is Zac using the jetski to peform the hydrographic survey.
Land & Sea Surveying's professional diver, Kyle, investigates, identifies, and marks the sea grass growth in the survey area.
Below are samples of various sea grasses collected for identification.
August 2016: Marco Island, Florida
Land & Sea Surveying Performed Pre and Post-dredge Bathymetric Surveys for the Collier Creek Dredging Project in Marco Island, Florida.
August 2016: Martin Marietta Port Canaveral
Land & Sea Surveying performed a survey to stake the boundary of a thirty-five-foot easement of the conveyor system for the Martin Marietta Port Canaveral Site.
July 2016: Port Everglades
Land & Sea Surveying team has just completed surveying services at Port Everglades, Terminal 18 for their gangways.
The above two images were provided by www.porteverglades.net
July 2016: Blue Origin Facility in Exploration Park.
Land & Sea Surveying team has been awarded the contract to provide surveying services for the construction of Blue Origin Facility in Exploration Park.
All imagines were provided by www.blueorigin.com/gallery
July 2016: Port Canaveral Port Authority
Land & Sea Surveying team just completed a right-of-way surveying project for Florida Department of Transportation (FDOT) and Port Canaveral Port Authority.
May 2016: Jupitor and Stuart, Florida
Land & Sea Surveying provided surveying services in Jupiter Florida and Stuart Florida to locate a submerged utility line. Additionally, a single beam hydrographic survey of the cable route through the waterbody utilizing a 200 kHz transducer with RTK GPS for horizontal and vertical positioning was completed at each location.
Land and Sea Surveying team utilizing the GPS equipment...
Site location below: The railroad bridge in Jupitor, Florida.
Land & Sea Surveying team used the MonArk vessel to run perpendicular lines in opposite directions across the cable with a receiver. The horizontal location of cable was also determined by a handheld submarine cable detector model 101...
In the field our team set all buoys to mark the location of the found utility line as shown below...
Below is the site location and Land & Sea Surveying team at work in Stuart Florida...
April 2016: Merritt Island
Land & Sea Surveying completes a hydrographic survey of Harbortown Marina using our 200 kHz single-beam transducer with RTK GPS for horizontal and vertical positioning.
April 2016: Stuart, Florida
Land & Sea Surveying team surveys the CSA survey vessel in Stuart, Florida. The survey of the ship sensors and locations of the R2Sonics multibeam transducer array, positioning sensors, USBL trans-sender, single beam transducer and the POS MV pitch, roll and heading values for set up in the multibeam acquisition software.
April 2016: Hopkins University
Land and Sea Surveying team supports John Hopkins University Applied Physics Lab in equipment and personnel support.
March 2016: Port Canaveral
Land and Sea Surveying team completed a multibeam suvery to Port Canaveral, Cruise Terminal 6.
March 2016: Sebastion Inlet
The semi-annual topographic and hydrographic surveying service for Sebastian Inlet has been completed.
March 2016: Kennedy Space Center
Land and Sea Survey provided hydrographic and topographic surveying support on the barge terminal at Kennedy Space Center.
March 2016: Port Canaveral, FL.
Land and Sea Survey competed a final as-built survey for Dutra Dredging at AS-1 B and an interim survey for AS-5A, Port Canaveral.
March 2016: Cocoa Beach, FL.
Our team has successfully completed the post survey for City of Cocoa Beach residential canals muck removal project starting in January 2016.
February 2016: McKim and Creed
Land and Sea Surveying is subcontracted to complete construction survey services for McKim & Creed in Fort Stewart and Fort Gordon Georgia.
February 2016: Daytona Beach
Land and Sea Surveying team preformed a topographic and boundary survey at Daytona Beach.
February 2016: Melbourne, FL.
Land and Sea Surveying teaming with Fish Tech. for dive assistance completed a subaqueous crossing inspection and hydrographic surviving services for the City of Melbourne in four different locations.
Fish Tech team visually inspecting PVC pipe on south side of Tortoise Island:
Fish Tech. dive vessel:
Pipeline of West side of US 192 Bridge...
Pipeline of the east side of US 192 bridge
The arrows indicate the pipeline west of the US 192 Bridge
Overall figure of Avenue B pipeline above
January 2016: Cocoa Beach Canals
Land and Sea Survey starts the new year completing a pre-dredging survey for residential canal maintenance dredging and muck removal for Cocoa Beach Canals.
Above is the Land and Sea Surveying crew muck probing the canal.
Below is the view of the entire Cocoa Beach canal that was sampled.
Land and Sea Surveying is using the Jet Ski to access the shallow water edges of each canal
December 21 2015: Space X
SpaceX launches and successfully lands the first stage of the Falcon 9 rocket at the new landing complex in Cape Canaveral, Florida.
Land & Sea Surveying is proud to have been a part of the construction of the new landing complex and Landing Zone 1 as well as construction of the launch facility at Complex 40.
Image courtesy of SpaceX.com
Image courtesy of SpaceX.com
Rocket launch above.
"Before" picture of the new construction of landing zone just above.
Just above is The Falcon 9 being lowered in for transport.
The new Landing Zone 1.
December 2015: KSC & CCAFS
Ending the year, Land & Sea Surveying continues surveying services supporting projects at KSC and CCAFS.